Construction of a transmission line occurs in phases. Often, pre-construction activities are performed within the right-of-way to allow National Grid to verify or collect new information that will aid in the construction of the new transmission line.
During field assessments and pre-construction activities, contracts will work within the existing easement to take samples, identify sensitive species, or clear vegetation.
Drilling small test holes to collect soil samples and evaluate ground conditions for structure foundations.
Using ground-penetrating radar to locate and map existing underground utilities or features before construction.
Field studies to identify protected species, habitats, or other environmental constraints in the project area.
Removing trees, brush, and other vegetation that could interfere with construction or safe operation of the line.
Once all regulatory agencies approve this Project the access for the construction equipment will be created. This will be done through removal or pruning of large trees and mowing approved access and work pads. Once the area is prepped for construction the base of each transmission line structure will be built. Once structures are in place the transmission line wire will be strung between the structures. After work is completed the land will be restored. Construction is anticipated to begin in 2029.
Preparing the transmission corridor and establishing temporary or permanent paths for crews and equipment to reach work areas.
Surveying and marking the precise locations where structures will be installed.
Excavating and constructing the concrete foundations that support transmission structures.
Delivering, assembling, and erecting poles on their foundations.
Stringing and securing the conductor wires, shield wires, and related hardware between structures.
Removing construction debris, stabilizing disturbed soil, and restoring the work area as close as practical to pre-construction conditions.
Visit our FAQs page to learn more about construction.